Interconnection Upgrade Project Marine Update – April 2017

  Spring Overview

The Project received permission to commence work for the Spring Cable Protection Phase in late March 2017.  In early April when ice levels in the Strait cleared, work commenced on the marine portion of the Interconnection Upgrade Project.

 Rip Rap Shoreline Protection was completed for all the near-shore trenching of the cables to reduce the chances of ice damage to the cables and coastal erosion.  Most of the remaining work in the Strait is in the offshore in water depths greater than 8 metres.  The focus has been the burial of the cables in the remaining (approximately) 20 kilometres, and some trench backfilling will be completed in the near shore of PEI and New Brunswick to finish the Cable Protection Phase.  The modifications made over the winter on the Trenching Remotely Operated Vehicle (or TROV) have been working well.  These modifications include modified teeth on the cutting chain to allow for quicker replacement, additional plates welded to the cutting chain to improve removal of loose material during cutting, optimized water flow through discharge hoses, and improved design for jetting swords  - they have been working well.  The modified chain cutter TROV followed by one or two TROV Jetting Passes to date trenched to the required depths and buried the cables successfully.  In early April, the crew/vessel moved around the ice in the Strait to complete the work plan.  The ice has now cleared from the Strait and should not have any further impacts on the project.  There have been some equipment breakdowns during this Period, but the crew has been able to fix problems in efficient timeframes.

 

2017 Short Term Restriction Zone and Fishers Fund

Transport Canada has established a safety zone of 500 metres around the Isaac Newton Cable Laying Vessel.  Maritime Electric representatives are monitoring and checking daily and confirming the specifications are met to bury and protect the cables.  Approximately 60% of the work is completed on the cables in the marine environment.  The Project applied to DFO for a short term fishing restriction for this year for a zone in SFA 22 for this year only.  Once the cables are buried, LS Cable will check to confirm  that cables have been covered to specifications and will complete a series of tests and surveys. There will be no long term fishing restrictions over the cables and the current requested restriction zone is a short term restriction for SFA 22 for 2017 scallop fishing season only.  The proposed restriction zone will commence May 1, 2017 and extend to the end of the scallop fishing season on June 3, 2017.  As requested by the fishers, buoys will also mark the short term restriction zone. The zone is approximately 500 metres around the Cable work site.

 LS Cable has established a fishers fund of $500,000 plus administration fees for First Nations and fishers who have scallop licenses in SFA 22 and the administration of the fund details are being finalized.   The fund is set up in trust currently in PEI with Maritime Electric’s lawyer.

  

Project Schedule

The Marine work for the Project will be completed this Spring and the revised Construction Schedule is noted below.  Restoration and landscaping of both on-land Project sites are underway.  The Energization Ceremony for the cables will occur this summer and the date is yet to be finalized.

 

Project Milestone Calendar

 

Milestone

Timeline

Installation Construction Method

Pre Trenching for Cable

May – July 2016

Out of the Strait before Lobster Season

In-Shore

(Borden-Carleton and Cape Tormentine)

Cape Tormentine Riser Station Construction

July 2016 – December 2016

On-Land

(New Brunswick)

Borden-Carleton Substation Construction

May 2016 – December 2016

On-Land

(Prince Edward Island)

Transmission Line Clearing – Melrose to Cape Tormentine

August - December 2016

On-Land

(New Brunswick)

Cable delivery to the Northumberland Strait & Cable Installation Commencement

October 2016

Marine

(The Northumberland Strait)

Cable # 3 Installation

October 2016 – December 2016

On-Land & Marine

Cable # 4 Installation

October 2016 – December 2016

On-Land & Marine

Testing, Commissioning

January 2017

On-Land

Transmission Line L1244 Clearing

January 2017 – February 2017

On-Land

(New Brunswick)

Transmission Line L1244 Construction

February 2017 – May 2017

On-Land

(New Brunswick)

Cable Mechanical Protection

April – June 3, 2017

*SFA 22 Proposed Restriction Zone May 1 – June 3, 2017

Marine

Overall Project Completion & Energization Ceremony

Spring 2017

TBD

On-Land & Marine

Updated April 25, 2017

 

 

   

 

Top-Left – Isaac Newton in Charlottetown Harbour in early January 2017; TROV on board Isaac Newton;

TROV with chain cutter arm; TROV in mini-mass flow excavator mode

 

 

 

Top-Left – Borden-Carleton Substation as of January 2017; Borden-Carleton Rip Rap Wall along the shore-line; Bottom– Isaac Newton in the Northumberland Strait during the cable pull-in procedure

 

   

 

Top-Left – Starfish performing backfilling in Cape Tormentine; Cape Tormentine site as of January 2017; Transmission line work along the Cape Tormentine to Melrose section; Cape Tormentine Rip Rap wall

 

IMG_0678 KP 14.000 Cable 4   Trencher on Deck   ROV being lowered to survey cable

 

IMG_0689 IMG_0686   SnipImage

 

Top-Left – TROV Jetting Swords; Diver’s photo of cable during inspection; TROV in Cutting Mode on Deck of Isaac Newton;

WROV being launched; Support Vessel conducting sediment surveys; Sediment Plume during Jetting Operations;

Type of Buoy to be used to mark exclusion zone

 

 

 Kim Griffin

Manager of Corporate Communications & Public Affairs

Official Corporate Spokesperson

Maritime Electric Company Limited

PO Box 1328,  180 Kent Street

Charlottetown, PE

C1A 7N2

griffinkm@maritimeelectric.com

T 902.629.3683

F 902.629.3665

www.maritimeelectric.com